We pleased to be able to share the good news that THCH have received confirmation from MHCLG that we have been successful in our bid for Building Safety Fund grant funding for cladding remediation for Bailey Tower and Harrison House. We are now in contract for the major works with Kier, who will undertake this work for us.

Project Timeline

Appointment of Principal Contractor (Kier Construction)

March 2021

Enabling and Opening Up Works

March/April 2021

Final Design Development with Contractor

April/May 2021

Principal Contractor Temporary Works Design Incl. Rail

April/May 2021

Principal Contractor Final Costing Review

June 2021

Principal Contractor Approval All Works

June/July 2021

Start on Site Main Works

July 2021

Handover

October 2022

Project Progress

In the meantime, we have also:

  • Recently completed the fire alarm installation to alert all residents of a fire now the blocks are on simultaneous evacuation.
  • Held ongoing discussions with the original developer, Bellway, about their contribution to the defective remediation works that are required.

What to expect in the coming weeks:

  • You will see both consultants and contractors working at your block in preparation for the main remediation work. This will include detailed survey work, where we will open up further and extensive parts of the building so that we can examine the construction behind the cladding. This additional preparatory work will help us to finalise the scope of remedial works that are required for your block.
  • Subject to some final testing  the fire alarm system will be fully operational.

Image

Paul Abraham

Paul Abraham is THCH's independent project manager leading on the Bailey Tower, Martineau Square and Harrison House fire safety cladding remediation project. He has extensive experience within the public and construction sectors and will oversee all consultants through the design stages along with the on-site construction stages utilising the specialist services of national contractor,  Kier Construction Ltd to ensure the successful delivery of the project; ensuring that THCH receive a quality service in a timely and cost effective manner.