Bailey Tower, Martineau Square and Harrison House
Latest update
We informed residents at our last residents meeting (August 2023) that the remediation project had been delayed from the initial expected completion date of May 2023, to late autumn 2023. The delay has been due to unforeseen weather, design and material supply issues. Whilst we cannot provide a specific completion date of all the works, the current aim is to be completed by the end of 2023. We are also planning to remove the welfare facilities and reinstate the paving and landscaping in January 2024.
Once the cladding works are fully complete, we will issue the updated EWS1 certificate. We thank you for your continued patience and cooperation.
Minutes from the most recent resident's meeting on 29 August 2023, are available below.
EWS1
An EWS1 form rates the external wall system of a building based on risk and combustibility. Find yours below.
Fire Risk Assessments
FRAs ensure our buildings are safe & identify any works that may be required. Find yours below.
The fire action advice for Bailey Tower, Martineau Square and Harrison House is to evacuate
For further information on this, visit our fire safety page.
Project phases
To give you an idea on timescales and what to expect with building safety work, we have created this project phase template. This provides a general overview of what to expect when your building is undergoing building safety works.
Bailey Tower, Martineau Sqaure and Harrison House are in phase 3.
Phase 1
Action
Assessment & findings
Timeline (approximately)
Six months
Communication
- Dedicated web page to store information and updates
- A reminder to let you know when we are doing your survey
- A letter shared with you with the findings
- You’ll have access to any certificates or reports
- You can ask us questions at any time
Risk mitigation
- Annual Fire Risk Assessment available to residents on our website, with actions followed up in timely manner
- Monthly health & safety inspections
- Where required, installation of heat sensor alarm
Phase 2
Action
Programme confirmation
Timeline (approximately)
Three months
Communication
- Dedicated web page to store information and updates
- Confirmation letters issued to lenders as required
- Expected successful remediation outcome, based on current government guidelines (B1)
- Depending on impact, you may be offered a resident meeting
Risk mitigation
- Annual Fire Risk Assessment available to residents on our website, with actions followed up in timely manner
- Monthly health & safety inspections
- Where required, installation of heat sensor alarm
Phase 3
Action
Remedial works begin on site
Timeline
3-14 months
Communication
- Dedicated web page to store information and updates
- Depending on scale of work, we will share monthly or quarterly email updates with you
- Single point of contact to raise issues (your Neighbourhood Officer)
Risk mitigation
Security measures taken place while on site e.g., CCTV on scaffolding/ secure hoarding
Phase 4
Action
Certification received
Communication
- Summary of project provided on dedicated web page
- EWS1 B1 certificate issued and stored on our website
Risk mitigation
New FRA / EWS1 issued
Project: what we've done
Appointment of Principal Contractor (Kier Construction) | March 2021 |
Enabling and Opening Up Works | March/April 2021 |
Final Design Development with Contractor | May 2021 |
Principal Contractor Temporary Works Design Incl. Rail | June 2021 |
Principal Contractor Final Costing Review | October 2021 |
Principal Contractor Approval All Works | December 2021 |
Start on Site Main Works | February 2022 |
Handover | May 2023 |
We have:
- Secured confirmation from the governments DLUHC Building Safety Fund grant for the cladding remediation works.
- Partially completed compartmentation firestopping works within the communal areas through the original developer, Bellway.
- Completed the fire alarm installation to alert all residents in the event of fire within the blocks which remain on simultaneous evacuation until all of the recladding and compartmentation works are complete. The fire alarm system is fully operational. The waking watch service shall continue to monitor the buildings during this period.
- We remain in discussions with the original developer, Bellway and the NHBC about their contribution to the defective fire safety remediation works that are required, including those firestopping works within the flats.
What to expect in the coming weeks:
- Kier are in possession of the site. With their permanent site compound in the Martineau Square due to the limited space available. We apologise for any inconvience this may cause.
- Kiers Resident Liaison Officer continues their presence on site and is available to answer any queries relating to their works.
- Fire alarm servicing of all detectors and panels within the blocks under immediate evacuation in the event of a fire breaking out.
- Our consultants shall continue to attend and monitor the areas affected by the recladding works as a record to ensure the highest quality is maintained.
Get in touch
We're here to help. If you have any concerns or queries, please do not hesitate to get in touch.
- Call our customer service team on 020 7780 3070
- Email us at customerservices@thch.org.uk
Paul Abraham, Bailey Tower's project manager, can also be contacted via e-mail at paul.abraham@thch.org.uk